Home/Free tools/Downtime cost calculator

// Free tool

Downtime cost calculator: price unplanned stops with your own numbers

Work out what an hour of unplanned downtime costs on each line or machine, using your own output rate, margin, crew and repair costs. Every number is yours. Every formula is on the page. Nothing you type is sent anywhere unless you choose to send it to us.

Loading the Downtime Cost Calculator (planned vs unplanned)… If nothing appears, please enable JavaScript.

// How it works

How the downtime cost calculator works

Each line or machine gets its own card. Results update as you type, totals add up across every line, and lines are ranked by annual unplanned cost. Download CSV exports that ranking with every input and output.

What you enter per line or machine

Input
What it means
Sch
Scheduled hours per week, including planned stops
Dp
Planned downtime hours per week (changeovers, preventive maintenance, sanitation)
Du
Unplanned downtime hours per week (breakdowns, jams, waiting on parts or material)
E
Unplanned stops per week
U
Normal output, units per hour
CM
Contribution margin per unit: price minus materials and other variable costs, excluding labor
n, r
Crew idled during a stop, and loaded hourly rate per person (wages plus benefits and payroll costs)
rec, ot
Share of lost output made up on overtime (0–100%), and the overtime multiplier
cs, cr
Scrap and restart cost, and repair cost (parts plus outside service), per stop

Two settings apply to every line: production weeks per year and an improvement scenario (X%). A blank or negative entry counts as zero, both percentages are capped at 0–100%, and any entry above one billion is treated as one billion.

Manufacturing downtime cost per hour: the formulas

  • Cost per unplanned hour = U × CM × (1 − rec) + n × r + rec × n × r × ot
  • Cost per minute = cost per unplanned hour ÷ 60
  • Weekly unplanned cost = Du × cost per unplanned hour + E × (cs + cr)
  • Annual unplanned cost = weekly unplanned cost × production weeks per year
  • Average stop length = Du × 60 ÷ E minutes (shown as “–” when no stops are entered)
  • Availability = (PPT − Du) ÷ PPT, where planned production time PPT = Sch − Dp (“–” when PPT is zero or less, “Check hours” when the result is negative)
  • Planned downtime = Dp × weeks per year, in hours, with an output value of Dp × weeks × U × CM. Shown separately, never added to cost
  • Savings at X% = annual unplanned cost × X%, assuming unplanned hours and stops both fall by X%

Read the hourly formula as three costs: lost margin on output you never make up, idle crew pay (counted either way), and overtime for output you do make up. Scrap, restart and repair are charged once per stop, not per hour.

The 1.5× overtime example is the federal floor: covered, non-exempt employees must get at least time and one-half their regular rate for hours over 40 in a workweek (U.S. Department of Labor). Enter your own multiplier if yours differs.

Why planned downtime isn’t added to cost

Changeovers, preventive maintenance and sanitation are on the schedule, so the calculator doesn’t treat them as losses. It uses them to work out availability and shows their hours and output value in a separate box. For stops that could go either way, see our guide to planned vs unplanned downtime.

Worked example (hypothetical)

These are the numbers the calculator opens with, not benchmarks or client data. Example line A is scheduled 80 hours a week, with 8 planned and 5 unplanned downtime hours across 12 stops. It makes 400 units an hour at a $1.25 margin, idles 5 people at $32 an hour, makes up 25% of lost output on overtime at 1.5×, and spends $75 on scrap and restart plus $120 on repair per stop, over 50 weeks a year.

  1. Lost margin: 400 × $1.25 × (1 − 0.25) = $375 an hour
  2. Idle crew: 5 × $32 = $160 an hour
  3. Overtime to make up output: 0.25 × 5 × $32 × 1.5 = $60 an hour
  4. Cost per unplanned hour: $375 + $160 + $60 = $595, or $9.92 a minute
  5. Weekly: 5 × $595 + 12 × ($75 + $120) = $5,315. Annual: $5,315 × 50 = $265,750
  6. Average stop: 5 × 60 ÷ 12 = 25 minutes. Availability: (72 − 5) ÷ 72 = 93.1%. Planned downtime: 400 hours a year, $200,000 of output, shown separately

Example machine B comes to $540 per unplanned hour and $168,000 a year. Together the two total $433,750 a year, with line A first at 61.3% of the total, and the 20% scenario shows savings of $86,750.

Assumptions and limits

  • Make-up output is assumed to take as long as the time lost, with the same crew.
  • Every stop on a line carries the same scrap, restart and repair cost, so enter averages.
  • Lines are priced independently: a stop that starves or blocks another line isn’t modeled, and there’s no blended cost per hour across lines.
  • Costs outside these inputs, such as expedited freight or late-delivery penalties, aren’t included.
  • The savings figure is a what-if, not a forecast. Amber “Check” notes flag hours that are missing or don’t add up (including more than the 168 hours in a week), unplanned hours with no stops, and an overtime share with no multiplier.

// No benchmarks

Why we don’t quote industry averages for the cost of downtime

Search for the cost of downtime in manufacturing and you’ll find figures per hour, per minute and per year that conflict widely. They depend on which industries were surveyed, how large the plants were and which costs were counted, and they often can’t be traced back to a primary study you could check.

None of them knows your line speed, your margin or your crew, so the calculator has no benchmarks built in. The example numbers are labeled hypothetical, and the result comes only from what you enter: a number you can walk through line by line with a plant manager or your finance team, and update when a rate changes.

Places to find the inputs:

  • Scheduled and planned hours: the production schedule
  • Unplanned hours and stops: your downtime log or shift reports
  • Contribution margin and loaded labor rates: finance or cost accounting
  • Repair costs: maintenance work orders and service invoices
  • Scrap and restart costs: quality or production records

// Measure it

Are your downtime hours measured or guessed?

Every dollar figure above rests on two inputs: unplanned hours and the number of stops. If they come from memory or an end-of-shift estimate, the cost is an estimate too. Measuring them means recording each stop as it happens: when it started, how long it lasted, what caused it and whether it was planned.

Our guide to tracking production downtime covers what to record. If you already keep a log, the downtime Pareto analyzer shows which causes matter most. It’s one of our free tools.

We build downtime tracking software and broader manufacturing data collection software around your reason codes and your rules for what counts as planned. Here’s what we built for Chelten House, a fourth-generation food manufacturer.

Manufacturing · Data collection

Production, traceability and downtime data from the plant floor

A custom application where Chelten House operators record production performance, product traceability and equipment downtime (planned vs unplanned, with causes and durations), stored in SQL Server to support their Tableau reporting.

Custom softwareSQL ServerTableau
Read the case study →

// FAQ

Downtime cost calculator FAQ

How do you calculate the cost of downtime per hour?

For each line, add the contribution margin on output you lose for good, the pay of the crew left idle, and any overtime needed to make up output later. Scrap, restart and repair costs are added once per stop. The formulas above show exactly how the calculator combines them.

Why don’t you show industry averages?

Published downtime-cost figures conflict widely and often can’t be traced back to a primary study. A number built from your own rates, margins and crew sizes is one you can defend. The example numbers in the calculator are hypothetical, not benchmarks.

What is contribution margin?

As used in this calculator: selling price minus materials and other variable costs, excluding labor. Labor is counted separately through the idle crew and overtime inputs, so it isn’t counted twice.

Why is planned downtime shown separately?

Planned stops like changeovers, preventive maintenance and sanitation are on the schedule. The calculator uses them to work out planned production time and availability, and shows their hours and the output not produced during them in a separate box. That value is never added to the cost of unplanned downtime. See planned vs unplanned downtime.

What if we make up lost output with overtime?

Enter the share you make up on overtime and your overtime multiplier. That share no longer counts as lost margin; it adds overtime pay for the idled crew instead, assuming the make-up time equals the time lost. Use 100% if you have spare capacity and no lost sales, and 0% if the output is simply lost. Idle crew pay during the stop is counted either way.

Are my numbers saved?

Only if you tick “Remember my inputs on this device,” which keeps a draft in this browser. Clear all removes it. Nothing you type is sent anywhere unless you choose to send it to us: “Send results to an engineer” opens our contact form with your results in the message box, and nothing goes out until you submit it. “Copy link” keeps your inputs after the # in the link, a part browsers don’t send to our server.

// Bring us in

Tell us about the software your business runs on.

A new build, a system that’s hard to use, a stuck project or a prototype that needs to go live. An engineer, not a salesperson, will get back to you.

202-88-MAGIC · or email info@effortlesspresence.com